Every policy, notification and order issued by the department on Electricity Duty, in one searchable place.
If any information found incorrect, or you have any advice or suggestion, please mail us at electricitydutyodisha@gmail.com
Odisha currently offers Electricity Duty exemption on renewable-energy-linked consumption through two separate policy instruments, and a developer must choose one — the two cannot be claimed together for the same project.
OREP 2022 (Odisha Renewable Energy Policy, 2022, including its 2026 amendments and Operational Guidelines) gives a smaller, fixed-rate benefit — 50 paisa/unit — but is sector-agnostic: any captive or open-access consumer, industrial or not, drawing power from an RE project set up in Odisha can claim it.
IPR 2022 (Industrial Policy Resolution, 2022, including its Operational Guidelines on ED exemption) gives a larger benefit — a full 100% ED exemption — but only to new industrial units in Priority or Thrust Sectors, or to any sector setting up a captive RE plant.
| Aspect | OREP 2022 | IPR 2022 |
|---|---|---|
| Nature of exemption | Partial — fixed at 50 paisa/unit on ED | Full — 100% exemption from ED |
| Who is eligible | Any captive or open access consumer (industrial or otherwise) consuming energy from an RE project set up inside Odisha | New industrial units in Priority or Thrust Sectors (or those undertaking Expansion/Modernization/Diversification), or units of any sector setting up a captive RE plant |
| Standard ED exemption period | 15 years from date of commissioning of the RE project | Priority Sector: 7 years; Thrust Sector: 10 years — from date of commencement of commercial production (on DISCOM power) |
| Extended / special period | Extended to 20 years if the RE project is commissioned before 30.03.2026 | 20 years for Green Hydrogen/Green Ammonia units; and 20 years, 100% ED exemption for units (Priority/Thrust/All Other Sectors) using captive RE plants |
| Net-metering consumers | New (2026 amendment): 50 paisa/unit ED exemption for 10 years from commissioning, if qualifying as a Captive Generating Plant under Electricity (Amendment) Rules, 2026 | Not separately addressed |
| Energy Storage Projects | ED exemption of 50 paisa/unit on input energy for 15 years from COD (if input sourced from in-state RE) | Not covered as a distinct category |
| Basis of consumption | Applies to consumption of RE-sourced power specifically (captive or open access, from RE projects in the state) | Applies to power from DISCOM/grid (for the sector-based exemption) OR to captive RE consumption (for the special RE-linked incentive) |
| Application / claim process | Claim filed with RE-SNA (GRIDCO) via Form-A within 6 months of commissioning/COD/availing supply; recommendation to Chief Engineer-cum-Chief Electrical Inspector; condonation up to 12 months (ACS) / beyond by Chief Secretary | Claim filed within 1 year of first commercial production; condonation by Secretary, Industries up to 24 months, beyond by Chief Secretary |
| Sanctioning authority | Chief Engineer-cum-Chief Electrical Inspector / Addl. CE-cum-Electrical Inspector, on recommendation of RE-SNA (GRIDCO) | Same authority structure, on recommendation via Industries Department / IPICOL channel |
| Mutual exclusivity | A developer must choose either OREP or IPR — cannot claim ED exemption incentives under both policies for the same project | |
Sources: OREP 2022 Resolution (30.11.2022) & Operational Guidelines; OREP 2022 Amendment Resolution (2026); IPR 2022 Resolution (30.11.2022), Section 4.5.2; IPR 2022 Operational Guidelines for Exemption of Electricity Duty.
Based on: (1) the Energy Department's letter/notification on auxiliary consumption dated 6.11.1999, (2) captive ED rate amendment records, 1986–2017, (3) the Odisha Electricity (Duty) Amendment Act, 2016 (Act 11 of 2016), (4) the Odisha Electricity (Duty) Amendment Rules, 2017, and (5) Notifications No. 5728 dated 26.5.2026 and No. 7819 dated 7.7.2026 on electrical safety inspection deregulation.
The Orissa Electricity (Duty) Act, 1961 (Act 14 of 1961) is the parent legislation under which duty is levied on energy consumed by consumers, payable to the State Government.
The Orissa Electricity (Duty) Amendment Act, 1986 (Act 9 of 1986) — notified 13.3.1986, effective retrospectively from 17.1.1986 — made several foundational changes:
Notification No. 7721/E dated 25.4.1992 fixed fresh rates effective 1.4.1992, including a key entry for energy supplied to power plants/industries having captive power plants without a Board supply agreement, at 25 paise/unit, and for any person not being a licensee/Board generating for own use, at 12 paise/unit.
Following the Supreme Court judgment in State of Mysore vs. West Coast Paper Mills Ltd, the Energy Department's letter dated 6.11.1999 (Letter No. 14246) clarified the duty treatment for ICCL/IMFA and other captive power plants:
A subsequent letter dated 6.3.2001 (Letter No. 3724) partially modified this, revising duty on auxiliary consumption to apply prospectively from 6.11.1999 rather than retrospectively, applicable to NALCO, ICCL, INDAL and other generating stations.
Notification No. 18237 amended the 1992 notification, raising the rate for self-generators from 12 paise to 20 paise per unit.
Notification No. 1-RE(ED)-26/2005, superseding the 1992 notification, shifted most categories from flat per-unit rates to a percentage-of-energy-charge model, with a cap of 25 paise/unit:
| Category | Rate |
|---|---|
| Irrigation / Agriculture | 2% of energy charge |
| Small Scale Industry (LT) | 4% |
| LT Non-Industrial | 4% |
| LT Industrial (excl. SSI) | 6% |
| HT Category | 7% |
| EHT Category | 8% |
| Self-generator (not licensee/Board) | 20 paise/unit |
| Licensee/Board own premises | 6 paise/unit |
| Public water works / Railway traction | Nil |
The Orissa Electricity (Duty) Amendment Act, 2010 (Act 10 of 2010) amended Section 3(1), raising the statutory duty cap from twenty-five to forty paise per unit.
Notification No. 8309 (issued as Odisha, post-renaming) superseded the 2006 notification and applied the new 40 paise cap: Irrigation 2%, LT Non-Industrial 4%, SSI 5%, LT Industrial 8%, HT 8%, EHT 9%. Self-generators and licensee/Board own-premises consumption rose to 30 paise/unit. A new provision brought Open Access / Special Agreement consumers under duty as if supplied by the licensee.
The Odisha Electricity (Duty) Amendment Act, 2016 substantially rewrote the parent 1961 Act. This is the single most consequential amendment in the chronology — it is the statutory basis that later permitted the captive/self-generation rate to jump to 55 paise/unit (see 12.5.2017 below).
The flat category-wise paise/unit schedule structure is replaced with a two-track ceiling:
Notification No. 617–BT(ED)-01/2016/En., dated 24.1.2017, amended the Odisha Electricity (Duty) Rules, 1961 — deemed to have come into force from 5.11.2016, the same commencement date as the 2016 Amendment Act, so that rules and parent Act took effect together:
Notification No. 9539–BT(ED)-01-2016/En, dated 27.12.2016, superseding Notification No. 8309 dated 1.10.2015, fixed the following Schedule of rates, effective 5.11.2016 (the commencement date of the 2016 Amendment Act) — issued under the newly substituted Section 3, still well within both the old 40-paise and new ₹2/unit ceilings:
| Sl. No. | Category of consumer or consumption | Rate of Electricity Duty |
|---|---|---|
| 1 | Irrigation Pumping and Agriculture (all supply voltages) | 2% of energy charge |
| 2 | L.T. Non-Industrial category | 4% of energy charge |
| 3 | Small Scale Industry [L.T. Industrial Supply] | 5% of energy charge |
| 4 | L.T. Industrial Category (excluding Small Scale Industry) | 8% of energy charge |
| 5 | H.T. Category | 8% of energy charge |
| 6 | E.H.T. Category | 9% of energy charge |
| 7 | Any person not being a licensee who generates energy for own use or consumption | 30 paise/unit |
| 8 | A licensee in its own premises | 30 paise/unit |
| 9 | Public water works and sewerage pumping, and Railway traction | Nil |
| 10 | Open Access Power (other than captive power), or power supplied by special agreement, or free of cost by the licensee | Same as it would have availed power from licensee |
This largely retained the 2015 structure (2%–9% slabs; captive/licensee at 30 paise/unit) but formalized Open Access Power (other than captive) as a distinct category (Sl. No. 10), taxed the same as licensee-supplied power. The notification also attached explanatory clarifications defining each category by supply voltage/contract demand — for instance, Small Scale Industry/LT Industrial Supply (Sl. 3) covers industrial consumers at voltage ≤ 650 V with contract demand below 22 KVA, HT (Sl. 5) covers voltage above 650 V up to and including 33,000 V, and EHT (Sl. 6) covers voltage above 33,000 V.
Notification No. 3442 amended the 2016 notification, raising the rate for self-generators (Sl. 7) and licensee-own-premises (Sl. 8) from 30 paise to 55 paise per unit. This increase — beyond the old 40-paise cap — was made possible only by the ₹2/unit statutory ceiling introduced by the 2016 Amendment Act.
Notification No. 5728/En, dated 26.5.2026, marks a shift in a related but distinct regulatory track from electricity duty: the safety inspection and certification of electrical installations under the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023:
Notification No. 7819/En, dated 7.7.2026, issued in partial modification of Notification No. 5728, narrows who may self-certify installations belonging to power utilities: electrical installations belonging to OHPC, OPGC and the DISCOMs up to 33 kV shall be inspected, tested and self-certified by the utility's own qualified and authorised electrical engineers — rather than through an independently-engaged CESE as under the original May notification. Issued under the same 2023 Safety Regulations.
| Effective date | Rate (paise/unit) | Statutory ceiling in force |
|---|---|---|
| 1.4.1992 | 12 | No statutory cap yet (Schedule rates under 1986 Act) |
| 10.10.2001 | 20 | No statutory cap yet |
| 1.1.2006 | 20 (unchanged) | 25 paise/unit cap (Explanation-1) |
| 1.10.2015 | 30 | 40 paise/unit cap (2010 Amendment Act) |
| 5.11.2016 | 30 (unchanged) | ₹2/unit (200 paise) cap (2016 Amendment Act) |
| 12.5.2017 | 55 | ₹2/unit (200 paise) cap |